1. The position of the package dyeing machine should be confirmed first, but before the installation, the maintenance and work space of the dyeing machine should be reserved for future operation and protection.
2. The dyeing machine should be installed on a relatively solid and flat foundation, and the dyeing machine should be fixed with the special screws of the foundation.
3. After determining the location of the dyeing machine installation, use a special instrument to check the dyeing machine, mainly to check whether its levelness meets the requirements. If the levelness is not correct, it needs to be corrected before installation.
4. Place the three-phase, four-wire and other power lines of the dyeing machine in a dedicated wire box for the machine.
5. During the installation process of the whole package dyeing machine, the dyeing machine should be grounded to ensure the safety of the daily use of the dyeing machine.
https://www.tonghuadyeingmachine.com/